ARC-BPAC December 2025 (rehearsal)
Monday 15 December 2025 -
06:00
Monday 15 December 2025
06:00
Accelerator operation issues and how they have been addressed
-
Kyo Shibata
Accelerator operation issues and how they have been addressed
Kyo Shibata
06:00 - 06:20
Issues ** Beam size increase due to beam-beam ** Small dynamic aperture (short Touschek lifetime) ** Low injection efficiency (2nd bunch control, orbit jitter, emittance increase at BT, beam-beam, emittance increase at a larger charge at Linac) ** Poor stability and reproducibility ** Lack of monitors ** SBL Summary of the work during the last shutdown to address those issues
06:20
Belle II operation issues and how they have been addressed
-
Katsuro Nakamura
(
KEK
)
Belle II operation issues and how they have been addressed
Katsuro Nakamura
(
KEK
)
06:20 - 06:35
Issues: ** Beam background (detector performance, detector life, DAQ stability) ** Detector damage by SBL ** Lack of on-site experts Summary of the work during the last shutdown to address those issues
06:35
Accelerator operation status
-
Makoto Tobiyama
Accelerator operation status
Makoto Tobiyama
06:35 - 06:55
Confirmed improvement by the work during the last shutdown Plan and result of 2025c run Issues in 2025c and how they have been addressed ** Hardware troubles and recovery procedures ** Physics run time less than 50% ** Lower injection efficiency than 2024c ** Lower specific luminosity than 2024c
06:55
Accelerator operation plan
-
Gaku Mitsuka
Accelerator operation plan
Gaku Mitsuka
06:55 - 07:15
How to achieve 1/ab and 1 x 10^35 /cm^2/s ** How to reach LER > 2.0 A and HER > 1.4 A, issues to be addressed to reach it, and how to address it. ** How to keep 80% of physics run time and how to improve the accelerator operation efficiency Machine studies Plan ahead for possible issues and contingencies
07:15
Mitigation plan for beam backgrounds and SBLs
-
Hiroyuki Nakayama
(
Belle (SuperKEKB Experiment)
)
Mitigation plan for beam backgrounds and SBLs
Hiroyuki Nakayama
(
Belle (SuperKEKB Experiment)
)
07:15 - 07:35
- Collimator - Faster beam abort - PXD HV fast shutdown - Belle II HV emergency shutdown interlock for machine failure
07:35
Belle II operation status & plan
-
Kenta Uno
(
KEK
)
Belle II operation status & plan
Kenta Uno
(
KEK
)
07:35 - 07:55
- Current status of the beam background, SBL, and DAQ - How the countermeasures for the issues are functioning in the operation or what improvements were confirmed during this run - Operation arrangements and expert staffing - Further improvements or implementation of remaining countermeasures - Detector studies - Strategy or criteria to turn on PXD